Week 12 (Apr.1 - Apr. 7th)
Currently working on tracking and hoping to finish by end of the week.

Week 11 (Mar.35 - Mar.31)
Finalized QA plan and recieved feedback from Priya.
Made timeline and prioritized outstanding issues in order to collect proper data.

Week 10 (Mar.18 - Mar.24)
Worked on quality assurance plan and writing test cases.

Week 9 (Mar.11 - Mar.17)
Spring Break. No progress.

Week 8 (Mar.3 - Mar.10)
Prepared for midsemester demo. Presented on March 6th.

Week 7 (Feb.25 - Mar.3)
Website is live.
Still awaiting for Raspberry Pi to arrive.
Putting parts together for mid-semester demo.

Week 6 (Feb.18 - Feb.24)
Projector & webcam arrived.
Testing the projector on film:

Week 5 (Feb.11 - Feb.17)
Presented modified idea along with the architecture.
Ordered parts.

Week 4 (Feb.4 - Feb.10)
Based off of reviews & budget contraints had to modify idea.
Had another design review with Priya.

Week 3 (Jan.28 - Feb.3)
Presented project proposal to class & received feedback.

Week 2 (Jan.21 -Jan.27)
Brainstormed & researched potential project ideas.
Had design review with Priya (via Skype).